ProjectLens Saved decisions

Check the schedule against the update

Compare two project schedules from Primavera P6 planning software with the written project update. See the evidence behind each change, then record the decision a person makes.

Runs in your browser. Your schedule files stay with you.

See a real public project: E-7 Wedgetail (real GMPP data) →

Northstar Grid ConnectionMade-up example
2 schedule files + written update

Changes to review

The finish moves 73 days but the update says unchanged

Previous finish15 Dec 2027
+73 days
Current finish26 Feb 2028
The update says
“The key completion date is unchanged.”
The schedules show

Scheduled finish moves by 73 days.

Next review question

What explains the revised finish?

From a changed date to a recorded decision

Review what moved, see the evidence, then record your decision and any follow-up conditions.

  1. Bring the update

    Add the previous and current schedule files (XER exports from Primavera P6) and the written update.

  2. Inspect what changed

    Read finish dates, fixed dates (constraints), links between tasks and spare time before the finish moves (float) beside the source fields.

  3. Ask the next question

    Keep a factual movement distinct from its explanation. Name an owner and due date for missing evidence.

  4. Keep the decision

    Record a human outcome and rationale. Export the evidence, then track any conditions.

The checks and their limits

ProjectLens compares the fields in your exports. A person interprets them and makes the decision.

Read the method
Do my schedule files leave this browser?

The standard review reads your files locally. Saving a draft or decision stores it on this device. Downloads give you a copy to keep or share. Optional public-record research is separately configured and receives narrative text, never XER files.

Does a flagged change mean the project is delayed?

A flagged change is a difference that needs review. Check its source and ask the owner to explain it. A later finish does not by itself prove why a project is late or who is responsible. These checks do not recalculate the critical path (the tasks that determine the finish), decide contractual rights or approve the change.

What can I compare?

Two schedule files (XER exports) from Primavera P6, each holding one project, from the same source project. ProjectLens checks their identity, dates and field coverage before comparing them. Missing fields and unsupported inputs are reported.

Turn a change pack into clearer questions

Start with the example, or review your own two schedule files.